Lake White: Lake White State Park Dam to Undergo Repairs

Posted on 1/16/2015 by Engineering in Lake White Dam

COLUMBUS, OH – The Ohio Department of Natural Resources (ODNR) and the Ohio Department of Transportation (ODOT) today announced notable capital improvement projects at Lake White State Park in Pike County. The most significant of these will be to make long-term risk reduction improvements to the 4,200-foot earthen dam to meet regulatory and safety requirements that are needed prior to restoring the lake level to its normal pool. ODOT also plans to replace the State Route 104 bridge that crosses over the dam spillway and other adjacent roadway improvements.

Click the READ MORE button for full posting.

read more..

Pond Lick Lake Dam: Spillway repairs completed

Posted on 1/16/2015 by Engineering in Pond Lick Lake Dam

Dam and spillway repairs are completed and a portion of the embankment has been seeded. Approximately 95 percent of all scheduled work at the site is complete. Asphalt paving and remainder of seeding and mulching of the dam is rescheduled for Spring, 2015.

read more..

Jefferson Lake Dam: Substantially completed

Posted on 1/14/2015 by Engineering in Jefferson Lake Dam

Jefferson Lake Dam - Construction was substantially completed by December 31, 2014. All remaining work and project closeout should be completed by Spring, 2015. Affected lake levels will be allowed to return to normal pool. (End of post.)

read more..

Tuscarawas Diversion Dam (PL): Construction substantially completed

Posted on 1/8/2015 by Engineering in Tuscarawas Diversion Dam

Construction was substantially completed by December 31, 2014. All remaining work and project closeout should be completed by Spring, 2015. Affected lake levels will be allowed to return to normal pool. (End of post.)

read more..

Roosevelt Lake Dam: Construction substantially complete

Posted on 1/8/2015 by Engineering in Roosevelt Lake Dam

Construction was substantially completed by December 31, 2014. All remaining work and project closeout should be completed by Spring, 2015. Affected lake levels will be allowed to return to normal pool. (End of posting)

read more..

Pond Lick Lake Dam: Construction substantially completed

Posted on 1/8/2015 by Engineering in Pond Lick Lake Dam

Construction was substantially completed by December 31, 2014. All remaining work and project closeout should be completed by Spring, 2015. Affected lake levels will be allowed to return to normal pool. (End of post.)

read more..

Pike Lake Dam: Construction substantially completed

Posted on 1/8/2015 by Engineering in Pike Lake Dam

Pike Lake - Construction was substantially completed by December 31, 2014. All remaining work and project closeout should be completed by Spring, 2015. Affected lake levels will be allowed to return to normal pool. (End of post.)

read more..