Project Updates

Mt. Gilead: Project work heading into final weeks

Posted on 10/26/2017 by Engineering in Mt. Gilead Lake Lower Dam

Substantial completion of dam and spillway improvements at Mt. Gilead Lake in Morrow County is scheduled for the end of 2017. Workers are near completion of rebuilding a new earthen embankment dam that will impound the lake.

Click "read more" below for photos and full article.

read more..

Acton Lake: Dam Improvements Completed at Hueston Woods

Posted on 10/23/2017 by Engineering in Acton Lake Dam

Improvements to the dam structure at Action Lake in Hueston Woods State Park have been completed.

read more..

Indian Lake: Spillway Replacement On Schedule in October

Posted on 10/20/2017 by Engineering in Indian Lake Dam

Demolition of the remaining old spillway at Indian Lake Dam is complete as workers prepare to begin construction of the eastern portion of a new labyrinth spillway.

read more..

Portage Lakes: East Reservoir, Work Ramping Up at Portage Lakes

Posted on 10/13/2017 by Engineering in Portage Lakes

Preparation activities increase ahead of East Reservoir Dam improvement project construction phase.

Click "read more" for full article.

read more..

Cutler Lake: Improvements underway as fall colors near peak

Posted on 10/11/2017 by Engineering in Cutler Lake

The spillway pedestrian bridge and portions of the spillway chute have been removed as Phase 1 excavation work continues.

Click "read more” for photos and full article.

read more..

Lake Loramie: New spillway structure taking shape

Posted on 10/6/2017 by Engineering in Lake Loramie Dam

Recently, workers have completed construction of the downstream wingwalls, initiated excavation of the downstream outflow channel and placed riprap between the wingwalls, among an expanded list of work items. Work upcoming includes installing the new sluice gate, stop logs and trash racks, completion of the concrete pour for the spillway control tower, placement of the riprap channel and installation of handrails. The project remains on schedule and is set for completion in Spring, 2018.

Click "read more" for photos.

read more..

Buckeye Lake: Structural Overview and Construction Process Update

Posted on 10/6/2017 by Engineering in Buckeye Lake Dam

With Phase II construction underway and with activity ramping up, we wanted to give you a quick overview of the Buckeye Lake Dam Rehabilitation Project and next steps.

Click "read more" below for full article with illustration and photo.

read more..