Roosevelt Lake Dam: Renovations currently in progress

Posted on 3/26/2014 by Engineering in Roosevelt Lake Dam

Renovations are currently in progress on the Roosevelt Lake Dam. Some of the work involves overtopping protection and renovations to the spillway, retaining walls and the lake drain system, which have required the lake to be drained. (Click REAM MORE button below for full article.)

read more..

Pike Lake Dam: Renovations in progress

Posted on 3/26/2014 by Engineering in Pike Lake Dam

Renovations to the Pike Lake Dam are currently in progress. Some of the work includes overtopping protection and replacing the spillway and lake drain systems, which have required the lake level to be drained. (Click the READ MORE button below for the full article.)

read more..

Lake Loramie Dam: Project Design and Cost Estimates Pending

Posted on 3/19/2014 by Engineering in Lake Loramie Dam

It is anticipated that the conceptual risk reduction project design and more detailed construction cost estimates will become available for ODNR to review at the end of 2014. (End of post.)

read more..

Acton Lake Dam: Construction began spring 2014

Posted on 3/16/2014 by Engineering in Acton Lake Dam

Renovations to the Acton Lake Dam began in March 2014. During construction, the archery range at the west end of the dam will be open, but parking will be limited. In addition, access to the dam, spillway, and downstream areas may be restricted at times. Visitors may experience heavy truck traffic along Loop Rd. and at access points to the park. We apologize for any inconvenience this may cause. The project is scheduled to be completed in winter 2015-16. (End of post.)

read more..

Pond Lick Lake Dam: Renovations in progress

Posted on 3/3/2014 by Engineering in Pond Lick Lake Dam

Renovations to the Pond Lick Lake Dam are currently in progress by Sunesis Construction Co., of West Chester. Included are improvements to the spillway. Construction is expected to be completed in Fall, 2014. Click the READ MORE button below for full article.