Your browser (Internet Explorer 7 or lower) is out of date. It has known security flaws and may not display all features of this and other websites. Learn how to update your browser.

X

Ohio.gov / search

Project Updates

Consultant Services Sought For Buckeye Lake Dam

Posted on 3/30/2015 by Engineering in Buckeye Lake Dam

ODNR took the first steps in the process of undertaking comprehensive dam improvements by advertising a Request For Qualifications (RFQ).

read more..

Dredging At Buckeye Lake To Begin Early April

Posted on 3/27/2015 by Engineering in Buckeye Lake Dam

Ohio State Parks staff began preparations this week for seasonal dredging activities at some of Ohio’s canal lakes, including Buckeye Lake.

read more..

Kasich Commits to Replacing Buckeye Lake Dam

Posted on 3/19/2015 by Engineering in Buckeye Lake Dam

Today Governor John R. Kasich, in a meeting with state and local officials and first responders, announced that the Ohio Department of Natural Resources (ODNR) will immediately begin work to replace Buckeye Lake Dam. A recent report by the United States Army Corps of Engineers (USACE) outlined serious structural deficiencies with the dam as well as options for reducing the risk to public safety posed by a catastrophic failure.

read more..

Buckeye Lake Dam Emergency Preparedness Steps Taken

Posted on 3/19/2015 by Engineering in Buckeye Lake Dam

On March 16, Ohio EMA and ODNR conducted an emergency preparedness meeting with state and local emergency management officials to discuss current emergency response plans and to encourage potentially impacted residents to be more prepared in the event of an incident involving Buckeye Lake Dam. The meeting was held in response to the recent report by the U.S. Army Corps of Engineers on the conditions of Buckeye Lake Dam.

read more..

Report on Buckeye Lake Dam Released

Posted on 3/11/2015 by Shaun Casbarro in Buckeye Lake Dam

The U.S. Army Corps of Engineers has issued its report to ODNR which is a review of past reports and existing conditions and recommendations for interim risk reduction measures, operation and maintenance at Buckeye Lake Dam. ODNR is reviewing the report; any decisions to be made will be announced soon.

read more..

Lake White Rapidly Filling!

Posted on 3/5/2015 by Engineering in Lake White Dam

Recent precipitation has rapidly filled the lake beyond desired levels. Action is underway to return the lake to an acceptable level until comprehensive repairs are made to the dam. Siphons that were placed at the dam above the spillway last September during an emergency response again being used at present to reduce the lake level.

read more..

U.S. Army Corps of Engineers’ report of its review of the condition of Buckeye Lake Dam

Posted on 3/4/2015 by Engineering in Buckeye Lake Dam

ODNR very soon will be issued the U.S. Army Corps of Engineers’ report of its review of the condition of Buckeye Lake Dam.

The report will include a review of past engineering reports and existing conditions at Buckeye Lake Dam and recommendations for risk reduction measures, operation and maintenance at the dam.

read more..