Mt. Gilead: Annual report for dam project available

Posted on 8/30/2017 by Engineering in Mt. Gilead Lake Lower Dam

On behalf of the Ohio Department of Natural Resources and in accordance with Part IX of the executed Memorandum of Agreement (MOA) for the Mt. Gilead Lake dam and spillways improvements project, the current annual report is being provided to consulting parties.
Download the 2017 Memorandum of Agreement - Annual Report from the Supporting Documents list here.

read more..

Lake Loramie: Annual report for dam project available

Posted on 8/30/2017 by Engineering in Lake Loramie Dam

On behalf of the Ohio Department of Natural Resources and in accordance with Part IX of the executed Memorandum of Agreement (MOA) for the Lake Loramie dam and spillways improvements project, the current annual report is being provided to consulting parties.
Download the Memorandum of Agreement from the Supporting Documents list here.

read more..

Mt. Gilead Lake: New Earthen Dam Work Now Underway

Posted on 8/24/2017 by Engineering in Mt. Gilead Lake Lower Dam

A unique aspect of the Mt Gilead Lake dam and spillway improvement project is that it includes a complete demolition and rebuild of the Lower Dam and its spillway and a rechanneled lake outflow. Also part of the project includes improvements to the Upper Dam that also are now underway. Much of the concrete work at the new Lower Dam has been completed, except pouring of the labyrinth columns. The stilling basin endsill and spillway baffles have been installed. Workers are returning previously removed soil to form a new earthen embankment that will impound Mt. Gilead Lake once it is allowed to refill. Additional design planning includes adding a hand-powered kayak/canoe public access for the lake. Project completion is scheduled for the end of 2017.

Click "read more" below for photos and full article.

read more..

Buckeye Lake: Proactive Water Control Management to Continue During Construction

Posted on 8/18/2017 by Dave Orr in Buckeye Lake Dam

ODNR will continue the practice of aggressive and proactive water control management during the construction period. Since the establishment of an interim summer pool, ODNR begins drawing down the lake to winter pool starting October 2nd. ODNR will follow this schedule again this year. Draw down to reach winter pool is expected to take approximately four (4) weeks or by the end of October- depending on weather, rainfall and other conditions. The stop-logs will be put back in place on March 1st and the lake will be allowed to refill to the interim summer pool, as done last year under the construction-period water control plan.

Click "read more" below for full article.

read more..

Indian Lake: Project Completion at Halfway Mark

Posted on 8/18/2017 by Engineering in Indian Lake Dam

Spillway and dam improvements at Indian Lake State Park are at 50 percent completion, according to ODNR. The $7.6 million project is scheduled for completion in Spring, 2018. Workers have finished concrete pouring and installation of the new labyrinth columns that form the new structure along the western half of the 700-foot long spillway. Phase II construction, which includes removal of the eastern half of the existing spillway and replacement with new labyrinth design concrete columns will soon begin.

Click "read more" below for full article with photos.

read more..

Portage Lakes: East Reservoir, Construction to begin after permits are issued

Posted on 8/11/2017 by Engineering in Portage Lakes

The dam remediation project is ready to move into construction as soon as environmental permits are finalized. ODNR is working with other agencies to complete the permitting phase and anticipate this will be forthcoming. When the permits are issued and construction activity begins, project stakeholders will be notified. Project completion remains Spring, 2019. 
End of article.

read more..

Cutler Lake: Lake level lowering continues as work begins

Posted on 8/9/2017 by Engineering in Cutler Lake

Workers have installed construction fencing, a temporary project sign, placed a job trailer, inspected the lake drain and established a work zone as the first phase of dam remediation begins at Blue Rock State Park. The lake sofar has been lowered five feet; target level is 13 feet below normal pool. Park visitors are reminded to stay clear of the construction zone.

Click "read more" for photos and full article.

read more..