Indian Lake: West Half of the New Spillway Completed

Posted on 9/22/2017 by Engineering in Indian Lake Dam

The cofferdam has been removed and construction completed on the west half of the new spillway at Indian Lake. This portion of the new spillway is now functional and controlling lake overflow.

Click "read more" below for full article with photos.

read more..

Cutler Lake: Dam improvement work underway

Posted on 9/21/2017 by Engineering in Cutler Lake

Lake dewatering has been completed and initial Phase I excavation has begun. Some partial trail closures are being maintained for the duration of the project.

Click "read more” for full article.

read more..

Portage Lakes: East Reservoir, work to begin after permitting

Posted on 9/13/2017 by Engineering in Portage Lakes

Improvement work at East Reservoir will begin when ODNR secures the necessary permits, which is expected soon. Scheduled project completion remains set for Spring, 2019. The work site is adjacent to Portage Lakes Drive between North Turkeyfoot Road and South Turkeyfoot Road. Local traffic in the work site will be maintained; flaggers may be present during the movement of heavy construction traffic.

read more..

Buckeye Lake: Crest Work to Begin

Posted on 9/12/2017 by Engineering in Buckeye Lake Dam

Starting mid-September crews will begin crest work on the old dam starting at Sellers Point and moving toward Liebs Island.

Click "read more" below for full article.

read more..