Project Updates

Buckeye Lake: Dock Fees Waived for 2018

Posted on 2/2/2018 by Engineering in Buckeye Lake Dam

Dock fees will be waived for the 2018 season. Homeowners and businesses may continue to use their docks.

Please click on "read more" link below for Dock Permit Application and full article.

read more..

East Reservoir: Dam Improvments Progress 1-24-2018

Posted on 1/29/2018 by Engineering in Portage Lakes

Several areas of construction are underway and progressing at the Portage Lakes East Reservoir Dam.

Click "read more" below for full article and photos of the progress so far.

read more..

Buckeye Lake: Construction Resumed; Remains on Schedule

Posted on 1/24/2018 by Engineering in Buckeye Lake Dam

Construction at Buckeye Lake resumed after the holidays and the overall project remains on schedule to be completed in late 2018.

read more..

Mt. Gilead: Substantial project completion near; final completion in spring  

Posted on 1/16/2018 by Engineering in Mt. Gilead Lake Lower Dam

ODNR anticipates that workers will attain substantial completion of project construction on the new dam and spillway prior to the end of January. Once accepted by ODNR, the lake will be allowed to slowly refill during the remainder of winter and into spring.

Click "read more" below for photos and full article.

read more..

Lake Loramie: Dam improvement project moving toward spring completion  

Posted on 1/16/2018 by Engineering in Lake Loramie Dam

Among the work completed during the past month includes completion of the bank floodwall construction, embankment placement, and placement of the upstream, downstream and swale riprap. The south cofferdam has been removed and site monitored during thawing and rain events.

Click "read more" full article.

read more..

Cutler Lake: Winter cold slows most construction activity

Posted on 1/9/2018 by Engineering in Cutler Lake

Much of Ohio’s outdoor construction activity was recently slowed by the holiday season and below normal winter temperatures.

Click "read more” for photos and full article.

read more..

Indian Lake: Project approximately 85 percent complete

Posted on 12/21/2017 by Engineering in Indian Lake Dam

Workers have nearly completed installation of the embankment berm and spillway cutoff wall sheets along the eastern portion of the spillway. The base of the spillway concrete pour is half completed. Winter concrete work will be completed in mid-winter.

Click "read more" below for full article with photos.

read more..