Project Updates

Lake Loramie: New spillway design in use as project nears completion

Posted on 12/12/2017 by Engineering in Lake Loramie Dam

Work over the past two weeks has included placement of the left embankment and installation of sheet piling. Lake refill between the two cofferdams was completed and now water is being held behind the new spillway, which features a labyrinth design.

Click "read more" full article.

read more..

Buckeye Lake: Construction Progress Update

Posted on 12/11/2017 by Engineering in Buckeye Lake Dam

With construction progress picking up speed through the holiday season, we wanted to share the latest news on the Buckeye Lake Dam Improvement Project.

Click "read more" below for full article.

read more..

Buckeye Lake: Change in Work Shift Plan

Posted on 12/1/2017 by Engineering in Buckeye Lake Dam

Please be advised that to efficiently and effectively finish a critical section of work from North Shore to just past the Buckeye Lake Yacht Club, DeWind will be implementing a 2-shift work plan beginning tomorrow, December 2. This will involve working from 6 AM to midnight from Saturday through Thursday of next week.

End of article.

read more..

Buckeye Lake: Review of Phase II Dam Construction and Goals for 2018 Completion

Posted on 11/22/2017 by Engineering in Buckeye Lake Dam

Review of phase II dam construction and goals for 2018 completion.

Click "read more" below for full article.

read more..

Mt. Gilead: Substantial project completion due in December  

Posted on 11/21/2017 by Engineering in Mt. Gilead Lake Lower Dam

Substantial completion of dam and spillway improvements at Mt. Gilead Lake is scheduled for December and expected to occur before Christmas.

Click "read more" below for full article.

read more..

Lake Loramie: Work continues through holiday period

Posted on 11/21/2017 by Engineering in Lake Loramie Dam

Many concurrent areas of construction work will continue through the coming holidays.

Click "read more" full article.

read more..

Cutler Lake: Preparation continues to ready for concrete work

Posted on 11/16/2017 by Engineering in Cutler Lake

Workers have been excavating and began subgrade cleaning in the area where dam improvements and a new spillway are to be constructed. This includes shaping the spillway foundation with a substance known as “dental concrete”, which typically consists of conventional concrete that is used to shape surfaces and fill irregularities as preparation prior to concrete structure pours. Construction work is to continue, weather permitting, through winter. Project completion is scheduled for Summer, 2018.

Click "read more” for photos and full article.

read more..