Cutler Lake: Concrete work commences as winter approaches

Posted on 12/12/2017 by Engineering in Cutler Lake

Workers remained on site and beginning the cold season with a diversity of concrete work as winter approaches. Forms are being constructed and workers will be pouring spillway and wingwall slabs, plus training walls, wingwall walls and the labyrinth weirs – the real core of the dam structure improvements. Workers also have been tying reinforcing steel and installing a waterstop. Construction activity remains on a six-day schedule per week. Project completion is scheduled for Summer, 2018.