Lake Loramie: Conditions ideal for concrete work at dam site

Posted on 6/30/2017 by Engineering in Lake Loramie Dam

Workers in June completed concrete placement for the spillway slabs, stilling basin slabs and wingwall footings. Backfill has been placed around the bank floodwall. Forming and concrete placement for the labyrinth cycles is underway, which shows the initial shape of the new spillway design. Overall, work progress is on schedule with project completion set for Spring, 2018.

Click below images for larger view.



Visit the Lake Loramie Dam Risk Reduction project page