The pace is fast and production is high as workers enjoy ideal conditions with the approach of summer at Lake Loramie State Park. Among recently completed work was concrete placement for the knee wall and stilling basin cutoff wall, concrete placement for the upstream cutoff wall and the center row of spillway slabs, installation of a drainage system under the spillway and stilling basin slab, and completion of backfill around the cutoff walls. Work underway includes continued concrete placement for the spillway slabs and stilling basin slabs. Project completion is scheduled for Spring, 2018.