Lake Loramie: New spillway design in use as project nears completion

Posted on 12/12/2017 by Engineering in Lake Loramie Dam

Work over the past two weeks has included placement of the left embankment and installation of sheet piling. Lake refill between the two cofferdams was completed and now water is being held behind the new spillway, which features a labyrinth design. The north cofferdam was to be removed. Work has been underway to excavate to subgrade and place substrate downstream over the rock channel. The project remains on schedule for completion in Spring, 2018.

Visit the Lake Loramie Dam Risk Reduction project page