Mt. Gilead: Upper dam improvements update

Posted on 6/15/2017 by Engineering in Mt. Gilead Lake Lower Dam

The new dam and spillway structure at Mt. Gilead State Park along Ohio Route 95 in Morrow County remains under construction. In recent weeks workers have completed installing basin slabs, upstream wing walls and structural anchors. Work on the walls, stems, embankment placement and concrete polishing remains ongoing and should be completed within the next 30 days. Also, work soon will resume on sediment removal and building the training wall concrete forms as part of the Upper Dam improvements. Project completion is scheduled for the end of 2017.

Construction site as of June 13, 2017


Visit the Mt. Gilead Dam Risk Reduction project page.

Mt. Gilead State Park web page.