Lake Loramie: Project updates provided at community meeting

Posted on 2/14/2018 by Engineering in Lake Loramie Dam

ODNR provided a project update Feb. 12 during the annual meeting of the Loramie Watershed Association. Construction of the new spillway and gate structure is complete. The new labyrinth spillway is currently in operation and replaces the former spillway located nearby. Monitoring and instrumentation have been installed. The new dam embankment is constructed and lake refill completed at the job site. Some additional work, including partial removal of the old spillway, site upgrades and grass planting will be completed in spring.

Click here to download a PowertPoint presentation used in this meeting. (6.3 Mb PDF)


Visit the Lake Loramie Dam Risk Reduction project page