Lake Loramie: Dam improvement project moving toward spring completion  

Posted on 1/16/2018 by Engineering in Lake Loramie Dam

Among the work completed during the past month includes completion of the bank floodwall construction, embankment placement, and placement of the upstream, downstream and swale riprap. The south cofferdam has been removed and site monitored during thawing and rain events.

Click "read more" full article.

read more..

Lake Loramie: New spillway design in use as project nears completion

Posted on 12/12/2017 by Engineering in Lake Loramie Dam

Work over the past two weeks has included placement of the left embankment and installation of sheet piling. Lake refill between the two cofferdams was completed and now water is being held behind the new spillway, which features a labyrinth design.

Click "read more" full article.

read more..

Lake Loramie: Work continues through holiday period

Posted on 11/21/2017 by Engineering in Lake Loramie Dam

Many concurrent areas of construction work will continue through the coming holidays.

Click "read more" full article.

read more..

Lake Loramie: New spillway structure taking shape

Posted on 10/6/2017 by Engineering in Lake Loramie Dam

Recently, workers have completed construction of the downstream wingwalls, initiated excavation of the downstream outflow channel and placed riprap between the wingwalls, among an expanded list of work items. Work upcoming includes installing the new sluice gate, stop logs and trash racks, completion of the concrete pour for the spillway control tower, placement of the riprap channel and installation of handrails. The project remains on schedule and is set for completion in Spring, 2018.

Click "read more" for photos.

read more..

Lake Loramie: Annual report for dam project available

Posted on 8/30/2017 by Engineering in Lake Loramie Dam

On behalf of the Ohio Department of Natural Resources and in accordance with Part IX of the executed Memorandum of Agreement (MOA) for the Lake Loramie dam and spillways improvements project, the current annual report is being provided to consulting parties.
Download the Memorandum of Agreement from the Supporting Documents list here.

read more..

Lake Loramie: Construction progress on schedule

Posted on 8/8/2017 by Engineering in Lake Loramie Dam

Workers have completed placement of the upstream concrete wingwall footings and currently are placing the downstream wingwall footings. Placement of the labyrinth cycles to the control joint remains underway. Concrete placement for training walls and wingwalls is completed. Temporary sheeting will be removed later this month and fill placement should be completed before end of the month. Work progress remains on schedule with project completion set for Spring, 2018.

Click "read more" for photos.

read more..

Lake Loramie: Conditions ideal for concrete work at dam site

Posted on 6/30/2017 by Engineering in Lake Loramie Dam

Workers in June completed concrete placement for the spillway slabs, stilling basin slabs and wingwall footings. Backfill has been placed around the bank floodwall. Forming and concrete placement for the labyrinth cycles is underway, which shows the initial shape of the new spillway design. Overall, work progress is on schedule with project completion set for Spring, 2018.

Click read more for photos.

read more..