Project Updates

Mt. Gilead: Refilling of lake underway

Posted on 2/14/2018 by Engineering in Mt. Gilead Lake Lower Dam

Refilling of Mt. Gilead Lake is underway following substantial completion of a project to construct a new dam and spillway. ODNR says the lake is about 2½ feet below normal pool and should reach full pool sometime in March.

Click "read more" below for photos and full article.

read more..

Mt. Gilead: Substantial project completion near; final completion in spring  

Posted on 1/16/2018 by Engineering in Mt. Gilead Lake Lower Dam

ODNR anticipates that workers will attain substantial completion of project construction on the new dam and spillway prior to the end of January. Once accepted by ODNR, the lake will be allowed to slowly refill during the remainder of winter and into spring.

Click "read more" below for photos and full article.

read more..

Mt. Gilead: Substantial project completion due in December  

Posted on 11/21/2017 by Engineering in Mt. Gilead Lake Lower Dam

Substantial completion of dam and spillway improvements at Mt. Gilead Lake is scheduled for December and expected to occur before Christmas.

Click "read more" below for full article.

read more..

Mt. Gilead: Project work heading into final weeks

Posted on 10/26/2017 by Engineering in Mt. Gilead Lake Lower Dam

Substantial completion of dam and spillway improvements at Mt. Gilead Lake in Morrow County is scheduled for the end of 2017. Workers are near completion of rebuilding a new earthen embankment dam that will impound the lake.

Click "read more" below for photos and full article.

read more..

Mt. Gilead: Annual report for dam project available

Posted on 8/30/2017 by Engineering in Mt. Gilead Lake Lower Dam

On behalf of the Ohio Department of Natural Resources and in accordance with Part IX of the executed Memorandum of Agreement (MOA) for the Mt. Gilead Lake dam and spillways improvements project, the current annual report is being provided to consulting parties.
Download the 2017 Memorandum of Agreement - Annual Report from the Supporting Documents list here.

read more..

Mt. Gilead Lake: New Earthen Dam Work Now Underway

Posted on 8/24/2017 by Engineering in Mt. Gilead Lake Lower Dam

A unique aspect of the Mt Gilead Lake dam and spillway improvement project is that it includes a complete demolition and rebuild of the Lower Dam and its spillway and a rechanneled lake outflow. Also part of the project includes improvements to the Upper Dam that also are now underway. Much of the concrete work at the new Lower Dam has been completed, except pouring of the labyrinth columns. The stilling basin endsill and spillway baffles have been installed. Workers are returning previously removed soil to form a new earthen embankment that will impound Mt. Gilead Lake once it is allowed to refill. Additional design planning includes adding a hand-powered kayak/canoe public access for the lake. Project completion is scheduled for the end of 2017.

Click "read more" below for photos and full article.

read more..

Mt. Gilead: Work to resume on Upper Dam improvements

Posted on 7/27/2017 by Engineering in Mt. Gilead Lake Lower Dam

In recent weeks, workers have completed construction of the training walls and downstream wingwalls of the new dam and spillway structures. Placement of stilling basins and general maintenance of drainage were completed, along with excavating the downstream outflow channel below the Lower Dam. At the Upper Dam, the haul road has been improved and preliminary earthwork continued. In the coming weeks, workers will be finishing concrete placement at the dam gate control tower, begin placement of the Lower Dam embankment and other general construction items. Project completion is scheduled for the end of 2017.

Click "read more" below for photos and full article.

read more..